Renewable power, benefits and challenges

GS-IIIInfrastructure

Note

Adding solar and wind capacity does not displace conventional capacity one for one, because their output is variable: solar generation peaks around midday while system demand peaks after sunset, so the evening ramp must be met from dispatchable sources. That temporal mismatch is the defining challenge, and the responses to it — storage, round-the-clock tenders, firm-and-dispatchable tenders that bundle variable generation with firm backing, and time-of-day tariffs that shift demand toward the generation window — are the corresponding instruments. Renewable shares of installed capacity and of generated energy diverge for this same reason, since capacity credit depends on when output arrives relative to when it is needed.

In the news

Newest first, each linking to its day

Economy, Industry & AgriculturePIB2 November 2026

Geothermal Energy ↗

Questions on this topic

From 20 October 2026The Hindu BusinessLine — Economy

Consider the following statements regarding the 'duck curve' problem and grid management challenges in high-solar-penetration power systems:Answer ▾
  1. The 'duck curve' arises because solar generation peaks during midday hours while net grid demand (total demand minus solar output) also peaks simultaneously, creating a surplus that strains transmission infrastructure.
  2. Battery Energy Storage Systems (BESS) are considered a structural solution to the duck curve because they can absorb excess solar generation during daylight hours and discharge it during evening peak hours when solar output falls to zero.
  3. In a grid with high renewable energy penetration, thermal power plants and short-term power purchases serve as flexibility resources to bridge the gap between the evening demand peak and the intermittent output of solar and wind generation.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is B

Explanation

Statement 1 is incorrect. The 'duck curve' does NOT arise because net demand peaks simultaneously with solar generation. The defining feature of the duck curve is the temporal mismatch: solar generation is highest during midday (creating a belly — oversupply or very low net demand), while actual grid demand peaks in the evening after sunset when solar output collapses to near-zero. This creates the characteristic duck-shaped net-load curve — a deep midday trough followed by a steep evening ramp. If both net demand and solar peaked simultaneously, there would be no grid-balancing problem; the problem is precisely that they peak at different times. Statement 2 is correct. BESS is the canonical structural solution to the duck curve: storage absorbs surplus solar electricity during the midday surplus period and injects it back into the grid during the evening peak, effectively shifting solar generation temporally to match demand. Statement 3 is correct. In high-renewable grids, dispatchable thermal capacity and short-term power market purchases act as flexibility resources — they can be ramped up during the critical evening hours when solar falls to zero and wind output is uncertain. This is exactly the role played by thermal plants and market purchases in a grid where renewable capacity alone cannot guarantee supply-demand balance at all hours.

From 24 October 2026Mint — Economy

Consider the following pairs regarding renewable energy integration and battery storage, in the context of India's 500 GW non-fossil capacity target by 2030:Answer ▾
  1. Intermittency of solar and wind power — necessitates battery energy storage systems and grid upgrades to balance supply and demand
  2. Critical minerals (e.g., lithium) — key raw material for rechargeable batteries used in electricity storage systems
  3. Grid modernisation — required independently of generation capacity expansion for reliable renewable energy integration

Which of the pairs given above is/are correctly matched?

Correct

Incorrect. The answer is D

Explanation

All three pairs are correctly matched. First, solar and wind power output varies with weather conditions and time of day — a fundamental characteristic of renewable generation known as intermittency — making battery storage and grid upgrades essential to manage fluctuations in supply and demand. Second, lithium is a critical raw material for most rechargeable battery technologies, including those used in grid-scale electricity storage; this is why access to lithium-rich countries (such as Australia, which produces a dominant share of the world's lithium) is strategically important for India's clean energy ambitions. Third, experts and policymakers consistently emphasise that expanding renewable generation capacity alone is insufficient — grid modernisation (transmission infrastructure, smart grids, load balancing mechanisms) must scale in parallel to absorb and reliably deliver variable renewable power. The principle here is that the 500 GW target has two indispensable pillars beyond generation: energy storage and grid infrastructure.

From 25 October 2026The Hindu BusinessLine — Economy

Consider the following statements regarding India's solar manufacturing value chain and the policy frameworks supporting domestic renewable equipment production:Answer ▾
  1. The Approved List of Models and Manufacturers (ALMM) framework in India operates at the module level, and its extension to cells (ALMM-II) is intended to mandate sourcing of domestically manufactured solar cells from an approved list, thereby incentivising upstream capacity creation.
  2. India's solar manufacturing capacity is concentrated at the module stage, with cell, ingot-wafer, and polysilicon capacities progressively diminishing up the value chain, reflecting a structural gap that increases dependence on imported upstream inputs.
  3. The Production-Linked Incentive (PLI) scheme for solar PV manufacturing in India disburses incentives based on installed capacity rather than actual production output, distinguishing it from other PLI schemes across sectors.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is A

Explanation

Statement 1 is correct. The ALMM framework requires that solar modules used in government-linked projects be sourced from manufacturers on an approved list. ALMM-II extends this logic upstream to cells, mandating that cells used in such modules also be domestically manufactured and listed — a tool to stimulate investment in cell capacity, which is the weakest link in India's solar value chain. Statement 2 is correct. India's solar manufacturing capacity follows a steep upstream deficit: module capacity is large (over 250 GW as of mid-2026), while cell capacity is a fraction of that, ingot-wafer capacity is minimal (approximately 2 GW), and polysilicon manufacturing is effectively absent. This pyramidal gap forces India to import the most technology-intensive upstream inputs, predominantly from China, making the country vulnerable to any supply disruption or export restriction from China. Statement 3 is incorrect. PLI schemes across sectors — including the solar PV PLI — disburse incentives linked to incremental sales or production output above a defined baseline, not on the basis of installed capacity. This output-linked structure is the defining feature of PLI schemes (as opposed to capital subsidies, which are disbursed on investment or capacity creation). The industry demand for a dedicated 'capital subsidy' for solar equipment manufacturing is precisely because PLI's output-linked nature may not sufficiently de-risk the upfront investment needed to build cell, wafer, and polysilicon capacity.

From Down To Earth

Consider the following statements regarding the grid-integration challenges posed by rooftop solar photovoltaic (PV) systems:Answer ▾
  1. Unlike conventional rotating generators, solar PV systems connect to the grid through inverters and do not inherently provide rotational inertia that helps stabilise system frequency after a disturbance.
  2. Under a net-billing arrangement, the rate paid to prosumers for electricity exported to the grid is typically set equal to the retail tariff they pay for consumption, ensuring revenue neutrality for the utility.
  3. Where rooftop solar generation exceeds local demand on a distribution feeder, electricity can flow back through the network, creating challenges related to voltage management and protection coordination.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is A

Explanation

Statement 1 is correct. Conventional generators have rotating machinery (turbines, alternators) that stores kinetic energy, providing inertia — a physical property that resists sudden changes in grid frequency when generation or load is disturbed. Solar PV systems, by contrast, interface with the grid through power-electronic inverters. Their capacity to support frequency and voltage is not inherent but depends on the inverter's design and programmed settings; without appropriate grid-following or grid-forming capability, large-scale simultaneous inverter disconnection during a fault can worsen the original disturbance. Statement 2 is incorrect. Net billing is specifically distinguished from net metering precisely because it does NOT pay the prosumer the full retail tariff for exported units. Under net billing, the export payment is set at a lower, administratively determined rate — as illustrated by Pakistan's shift from approximately PKR 26 per kWh (closer to retail parity under net metering) to PKR 10–13 per kWh under net billing. This reduction in the compensation rate for exports, combined with shorter contract periods, is the defining financial feature of net billing and the reason it reduces utility revenue shortfalls compared with net metering. Statement 3 is correct. When distributed solar generation on a feeder exceeds the local load being served, surplus electricity flows back upstream through the distribution network — a 'reverse power flow'. This is operationally significant because distribution networks were originally designed for unidirectional power flow (substation to consumer). Reverse flows can elevate feeder voltages beyond permissible limits, overload transformers or conductors rated for one-directional current, and confuse conventional protection relays that assume fault current flows only from the grid toward the consumer. Managing these effects requires updated protection coordination and voltage-regulation strategies.

From 26 October 2026The Hindu BusinessLine — Economy

Consider the following pairs regarding the solar photovoltaic (PV) manufacturing value chain and India's domestic sourcing framework:Answer ▾
  1. Polysilicon — The most upstream raw material in the solar PV value chain, used to produce ingots
  2. Approved List of Models and Manufacturers (ALMM) — A mandatory sourcing framework under MNRE that governs which solar components qualify for use in Indian solar projects
  3. Ingots — A stage in the solar PV value chain where China holds a near-monopoly over both the final product and the equipment used in its production

Which of the pairs given above is/are correctly matched?

Correct

Incorrect. The answer is C

Explanation

All three pairs are correctly matched. First, polysilicon is indeed the most upstream feedstock in the solar PV manufacturing value chain — the sequence runs polysilicon → ingot → wafer → cell → module, and polysilicon is the starting material. Second, the Approved List of Models and Manufacturers (ALMM) is MNRE's mandatory sourcing instrument: only products and manufacturers listed on it may be used in government-supported solar projects in India, giving it the character of a localisation mandate. Third, ingots occupy a uniquely China-dependent position in the value chain — unlike cells, wafers, or polysilicon where non-Chinese suppliers exist, China holds a near-monopoly over ingot production as well as the equipment (e.g., Czochralski pullers) used to make them, making this segment the most vulnerable to supply-chain disruptions.

From 26 October 2026The Hindu — National

Consider the following statements regarding pumped storage hydropower (PSH) projects and their role in integrating renewable energy into the grid:Answer ▾
  1. Pumped storage hydropower functions as a form of grid-scale energy storage by using surplus electricity — typically generated during periods of low demand — to pump water to an upper reservoir, which is then released to generate electricity during peak demand hours.
  2. The primary rationale for pairing pumped storage projects with solar energy expansion is that solar generation drops sharply after late afternoon, creating an evening peak-demand gap that PSH is designed to fill, thereby reducing reliance on coal-fired peaking power.
  3. Unlike conventional hydropower, pumped storage projects require a significantly larger land footprint for comparable installed capacity, which is why they are generally located away from ecologically sensitive zones.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is D

Explanation

Statement 1 is correct. Pumped storage hydropower is the dominant form of utility-scale electricity storage globally. During low-demand or high-generation periods (e.g., when solar output is high midday), excess electricity is used to pump water from a lower to an upper reservoir. When demand peaks, water is released back through turbines to generate electricity — effectively acting as a rechargeable battery. Statement 2 is correct. The core grid-balancing argument for PSH alongside solar is precisely the solar intermittency problem: solar PV produces electricity abundantly during daylight hours but output falls to near-zero after sunset, while household and commercial electricity demand typically peaks in the evening (roughly 6–10 p.m. in India). PSH bridges this gap by storing solar-period surplus and dispatching it during the evening peak, displacing coal-fired peaking plants that would otherwise be needed. Statement 3 is incorrect. One of the distinctive engineering advantages of pumped storage projects over conventional run-of-river or storage hydropower is that they require a comparatively smaller land footprint for equivalent installed capacity, because their design is based on hydraulic head (elevation difference between two reservoirs) rather than large reservoir surface area. The Karjat project, for instance, claimed a land requirement approximately 52 times lower than a conventional hydropower project of comparable capacity — the opposite of what Statement 3 asserts. The ecological sensitivity concerns around PSH projects arise mainly from forest clearance for civil infrastructure, not from an inherently larger land requirement.

From 26 October 2026Indian Express Explained

Consider the following statements regarding agri-photovoltaics (agri-PV) and its integration under the PM-KUSUM scheme:Answer ▾
  1. Agri-PV panels are installed at a greater height than conventional ground-mounted solar panels in order to allow farming operations, including the movement of machinery, to continue underneath them.
  2. Agri-PV projects have been found suitable for crops such as rice and sugarcane, but initial assessments indicate they are not well-suited for fruits and leafy vegetables.
  3. The dual land-use model of agri-PV is intended to address land scarcity for solar deployment by enabling large-scale solar installations on agricultural land without fully displacing cultivation.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is A

Explanation

Statement 1 is correct: agri-PV requires elevated panel structures — installed at around 3.5 to 4 metres above the ground — precisely so that farmers can continue routine agricultural operations, including the movement of farm machinery, beneath the panels. This is what distinguishes agri-PV infrastructure from standard ground-mounted solar installations, and what makes it around 25–30% more expensive. Statement 2 is incorrect: it inverts the government's own assessment. Initial studies indicate that agri-PV is suitable for fruits and leafy vegetables — crops that can tolerate partial shade — but has not been found suitable for crops such as rice and sugarcane, which require higher levels of direct sunlight. The statement has this relationship backwards. Statement 3 is correct: the fundamental rationale for integrating agri-PV under PM-KUSUM is to resolve the tension between the large land footprint of solar energy and the scarcity of non-agricultural land, especially in states with limited non-farm area. By co-locating solar generation with food production, the model aims to expand renewable capacity without fully displacing agriculture, thereby protecting food security.

From 26 October 2026The Hindu BusinessLine — Economy

Consider the following pairs regarding India's solar manufacturing policy framework:Answer ▾
  1. ALMM — Approved List of Models and Manufacturers from which DCR-compliant modules must be sourced
  2. Domestic Content Requirement (DCR) — a condition mandating that solar cells and modules used in certain government schemes be made in India
  3. PLI scheme for solar — incentivises backward integration into ingots, wafers and cells, not just module assembly

Which of the pairs given above is/are correctly matched?

Correct

Incorrect. The answer is A

Explanation

All three pairs are correctly matched. First, the ALMM (Approved List of Models and Manufacturers) is the government-maintained list that module manufacturers must appear on before their products can qualify as domestically made; the ALMM-II framework specifically extends this requirement to solar cells. Second, the Domestic Content Requirement (DCR) is a well-established condition under schemes such as JNNSM (Jawaharlal Nehru National Solar Mission) that requires solar cells and modules procured for government projects to be manufactured within India — a measure designed to prevent dumping of imported equipment. Third, India's Production-Linked Incentive (PLI) scheme for high-efficiency solar modules was designed expressly to incentivise investment not just in final module assembly but in the deeper, upstream stages of the value chain — ingots, wafers and cells — so as to reduce import dependence on China. China's proposed export curbs on photovoltaic manufacturing technologies directly threaten this backward-integration agenda and the ALMM-II timelines, since Indian manufacturers planning to enter capex cycles for these upstream stages now face potential technology and equipment access constraints.

From Down To Earth

Consider the following statements regarding the PM-KUSUM scheme and its three components:Answer ▾
  1. Component A of PM-KUSUM supports decentralised grid-connected solar power plants, which are distinct from stand-alone solar pumps that have no grid connectivity.
  2. Component B of PM-KUSUM, which supports stand-alone solar pumps, requires coordination with electricity distribution companies (DISCOMs) for power purchase agreements, making it more complex to implement than Component A.
  3. Component C of PM-KUSUM focuses on the solarisation of existing grid-connected agricultural pumps and feeders, and its implementation involves multiple stakeholders including state agencies, DISCOMs, regulators, developers and landowners.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is D

Explanation

PM-KUSUM was launched in 2019 under the Ministry of New and Renewable Energy (MNRE) with three distinct components. Component A supports decentralised grid-connected solar power plants — these are small solar plants set up near agricultural land and connected to the grid, distinct from stand-alone (off-grid) pumps. Statement 1 is correct in drawing this distinction. Statement 2 is incorrect: it is Component A (grid-connected decentralised plants) and Component C (feeder/pump solarisation) that require DISCOM involvement for power purchase and grid coordination, not Component B. Component B stands for stand-alone solar pumps, which by definition operate independently of the grid and therefore do not require DISCOM power purchase agreements — this is precisely why Component B achieved nearly 90 per cent of its target while Components A and C lagged. Statement 3 is correct: Component C involves solarisation of existing grid-connected agricultural pumps and feeders, and its implementation inherently requires coordination among state agencies, DISCOMs, regulators, developers, lenders and landowners — accounting for its uneven progress across states.

From Down To Earth

Consider the following statements regarding India's renewable energy expansion and the policy instruments supporting it:Answer ▾
  1. India permits foreign direct investment of up to 100 per cent in the electricity sector, and has established renewable energy parks that provide land and transmission access to developers.
  2. Viability gap funding (VGF) in India's renewable energy sector is a mechanism under which the government provides capital grants to make commercially unviable but socially desirable renewable energy projects financially attractive to private investors.
  3. Payment reforms in India's renewable energy sector have been directed primarily at generation companies, requiring them to provide transmission charge exemptions to electricity distribution companies in order to reduce outstanding dues.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is C

Explanation

Statement 1 is correct: India allows 100 per cent FDI in the electricity sector under the automatic route, and renewable energy parks are a policy instrument that bundles land acquisition and transmission connectivity, lowering entry barriers for developers — both features are well-established in India's renewable energy policy architecture. Statement 2 is correct: Viability Gap Funding is a government grant mechanism designed to bridge the gap between the cost of developing a project and the revenue it can realistically generate, making it commercially viable for private sector participation — it is a standard instrument under India's infrastructure policy, applied to solar and wind projects where tariffs alone may not cover capital costs. Statement 3 is incorrect in its attribution of mechanism and direction: transmission charge exemptions are granted TO renewable energy generators/consumers (not by generators to discoms), and payment reforms have been directed at improving the financial health of electricity distribution companies (discoms) so that they honour their payment obligations to generators — the direction of obligation is inverted in the statement. The decline in discom arrears is a consequence of demand-side (discom) payment reforms, not a benefit extended by generation companies.

From 1 November 2026Indian Express Explained

Consider the following pairs regarding concepts central to integrating variable renewable energy into an electricity grid:Answer ▾
  1. Inverter ride-through settings — Ability of a rooftop solar inverter to remain connected to the grid during temporary voltage or frequency disturbances, rather than tripping immediately
  2. Under Frequency Load Shedding (UFLS) — A protection mechanism that automatically disconnects selected generation sources to increase supply and restore grid frequency
  3. Non-dispatchable generation — Power sources whose output depends on weather conditions and cannot be readily ramped up or down by grid operators

Which of the pairs given above is/are correctly matched?

Correct

Incorrect. The answer is D

Explanation

Pair 1 is correctly matched: inverter ride-through settings (also called low-voltage and frequency ride-through) are configurations that allow rooftop solar inverters to stay connected to the grid during brief deviations in voltage or frequency, preventing a cascade of simultaneous disconnections that can deepen a generation deficit. Pair 2 is incorrectly matched: Under Frequency Load Shedding (UFLS) automatically disconnects selected electrical loads (i.e., demand/consumers), not generation sources, in order to reduce demand and thereby stabilise grid frequency when supply suddenly falls short. UFLS is a demand-side emergency tool, not a supply-side one. Pair 3 is correctly matched: non-dispatchable generation refers to renewable sources such as rooftop solar and wind whose output is weather-dependent and cannot be commanded to increase or decrease output in the way that conventional dispatchable plants (coal, hydro, gas) can be. The distinction between dispatchable and non-dispatchable generation is foundational to understanding grid frequency management challenges as India scales up rooftop solar.

From 6 November 2026The Hindu — National

Consider the following statements regarding Battery Energy Storage Systems (BESS) and their role in renewable energy integration and grid stability:Answer ▾
  1. One of the primary functions of grid-scale battery storage is to absorb surplus renewable energy during periods of high generation and release it during peak-demand hours, thereby reducing the need for expensive short-term power purchases.
  2. Renewable energy curtailment — the deliberate reduction of output from wind or solar plants — occurs when grid supply exceeds demand and adequate storage or flexible load capacity is unavailable to absorb the surplus.
  3. Installing battery storage alongside solar projects (co-location) reduces intermittency but does not contribute to peak-demand management, since peak demand and solar generation coincide during daytime hours.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is D

Explanation

Statement 1 is correct: a core purpose of grid-scale BESS is temporal shifting of energy — storing surplus renewable generation (which would otherwise be curtailed or wasted) and discharging it during evening or other peak-demand windows, thereby displacing costly spot-market or short-term power purchases. Statement 2 is correct: renewable curtailment happens precisely when instantaneous supply exceeds demand and there is no mechanism (storage, flexible load, or export capacity) to absorb it — battery storage directly addresses this by acting as a sink for excess generation. Statement 3 is incorrect: solar generation peaks around midday, while electricity demand typically peaks in the morning and again in the evening. Co-located BESS can store midday solar surplus and discharge it during the evening peak — which is exactly the peak-demand management function. The claim that co-location 'does not contribute to peak-demand management' because generation and peak demand coincide is factually wrong; it is the temporal mismatch between midday solar generation and evening peak demand that makes storage valuable for peak management.

From 6 November 2026The Hindu BusinessLine — Economy

Consider the following statements regarding the renewable energy landscape in India, particularly in the context of solar PV, onshore wind, and grid integration:Answer ▾
  1. In India, onshore wind generation exhibits pronounced seasonal fluctuations — peaking during the monsoon season and declining significantly during the rest of the year — making it less complementary to solar PV compared to such seasonal pairing in regions like the European Union.
  2. Pumped-storage hydropower serves as a grid-integration tool that helps manage variability in renewable output by storing surplus electricity during periods of high generation and releasing it when generation falls, thereby smoothing supply-demand mismatches.
  3. Solar PV in India is considered inherently more variable than onshore wind on a seasonal basis, because rooftop solar output fluctuates sharply across monsoon and non-monsoon months owing to cloud cover.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is D

Explanation

Statement 1 is correct. A core challenge in India's renewable mix is that wind and solar generation profiles are not highly complementary on a seasonal basis. Wind output surges during the monsoon but drops sharply outside it, whereas solar output remains comparatively stable across seasons. This contrasts with certain European contexts where wind and solar can complement each other more effectively across seasons, thereby reducing overall grid variability. Statement 2 is correct. Pumped-storage hydropower is a proven grid-balancing technology: surplus renewable electricity (e.g., from midday solar peaks) is used to pump water uphill into a reservoir; when demand rises or generation falls, water is released through turbines to generate power. This makes it a critical storage and variability-management tool for grids with high renewable penetration. Statement 3 is incorrect. The IEA's characterisation is precisely the opposite: solar PV generation in India remains comparatively stable across all seasons, with relatively small monthly variations. It is onshore wind that introduces the greater seasonal variability. The combined wind-solar generation profile is therefore dominated by wind's monsoon seasonality, resulting in a more variable aggregate output — not because solar is volatile, but because wind is.

From 11 November 2026The Hindu BusinessLine — Economy

Consider the following statements regarding India's wind energy sector and its repowering strategy in the context of the 500 GW non-fossil capacity target by 2030:Answer ▾
  1. Wind power repowering involves replacing older, smaller turbines at existing sites with larger, more efficient units, allowing capacity to be increased without acquiring additional land.
  2. India's wind energy installations have kept pace with solar energy additions since 2014, with both sectors expanding at broadly comparable rates.
  3. Limited battery storage combined with insufficient daytime generation from solar sources has been identified as a key reason for electricity shortfalls during peak evening hours in India.

Which of the statements given above is/are correct?

Correct

Incorrect. The answer is D

Explanation

Statement 1 is correct. Wind power repowering is precisely the strategy of replacing older, low-capacity turbines with modern, high-capacity units at already-established wind farm sites, thereby boosting output without the need for new land acquisition. This addresses one of India's primary barriers to faster wind deployment — difficulty in acquiring new land and securing right-of-way. Statement 2 is incorrect. Wind installations in India have significantly lagged behind solar additions; India's green power capacity has grown substantially since 2014, but wind energy deployment has not matched solar's pace, with land acquisition remaining a persistent hurdle. Statement 3 is incorrect. The grid challenge described is the reverse: limited battery storage combined with EXCESS daytime solar generation leads to solar curtailments (wasted power), while inadequate firm dispatchable capacity creates shortfalls at night. It is the abundance of solar power during the day — not insufficient generation — that creates the mismatch, alongside insufficient storage to shift that surplus to evening demand.